  • Apply through Cloudpermit
  • Initial review: 10 business days

Do you need a permit for a home addition in Grimsby?

Yes. Additions need a building permit, and the Town reviews them against the Building Code, zoning and the Escarpment and conservation rules.

Needs a building permit

  • Additions of any size, including second storeys
  • Rooms over a garage
  • Bump-outs
  • Decks and porches
  • New or bigger window and door openings

Usually no permit

  • Painting and decorating
  • New flooring
  • Replacing cabinets with no plumbing changes

Zoning still applies even when no permit is needed. The Town doesn't issue electrical permits. Those go to the Electrical Safety Authority.

What does the Town need with the application?

From the Town of Grimsby's permit checklist. Incomplete applications aren't accepted for processing.

Site and grading plan

Existing and new grades, distances to property lines, the driveway, swales, downspouts and where the water goes.

Foundation plan

Footing locations, sizes and depths. Helical piers need engineering and a CCMC approval.

Floor and roof plans

Rooms, dimensions and every joist, beam, rafter and column size. Engineered joists and trusses need the maker's stamped design.

Elevations and section

Every side of the house, window and door sizes, heights, and a cross section from footing to roof.

Heating design

Heat loss and gain, the duct layout and a ventilation summary.

Forms

The application, the Schedule 1 designer form and the energy efficiency design summary.

How long does an addition permit take in Grimsby?

Apply on Cloudpermit, or at the Town Hall kiosk between 8:30 a.m. and 4:30 p.m.

  1. 1

    Apply

    Online through Cloudpermit or at the kiosk with a building staff member.

  2. 2

    Initial review

    10 business days for a complete residential application.

  3. 3

    Comments

    Each resubmission can add 2 weeks or more. The Town's average for residential alterations is about 7 weeks.

  4. 4

    Permit issued

    Work has to start within 6 months, and the permit stays posted on site.

  5. 5

    Inspections

    Nothing gets covered until the inspector passes it.

Brick house with a new one-storey side addition

When do the Escarpment and the NPCA come into it?

Grimsby sits between Lake Ontario and the Niagara Escarpment, so some lots need another agency's sign-off before the building permit.

  • Niagara Escarpment Commission development permit, for lots in its regulated area
  • Niagara Peninsula Conservation Authority permit, for lots in its regulated area
  • A heritage review for designated buildings and heritage districts
  • No building under overhead power lines, and a check on lines within 5.5 m
Book a site visit

Grimsby addition permit questions

Do I need a permit for an addition in Grimsby?

Yes. Apply through Cloudpermit or at the Town Hall kiosk.

How long does the permit take?

The first review is 10 business days for a complete application. The Town's average for residential alterations is about 7 weeks.

What is the minimum permit fee?

The Town lists a $232 minimum for 2026. The full fee is based on floor area.

Do I need a Niagara Escarpment permit?

Only if the lot is in the Niagara Escarpment Commission's regulated area. The Town's checklist asks about it.

Can I draw my own plans?

The Town allows owners to prepare their own drawings for houses under Part 9 of the Building Code. Most people hire a designer.

Who does the electrical permit?

The Electrical Safety Authority. The Town doesn't issue electrical permits.

Finished basement living room with a large sectional

Book a site visit

Tell us about your house and what you want to add and we'll call you back to set up a visit.

By sending this, you agree we can share your request with a contractor who serves your area. See our privacy policy.

Start with a look at your house

A site visit shows what your lot allows and what an addition would involve.

Book a site visit 416-995-4534